Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

STL - Formerly Best Training Solutions Through Learning
TrustPilot
Excellent
Request Callback We will call you back
0207 987 3777 Call for assistance
Your Basket Basket is empty
microsoft professional project server training - what defines baseline

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft professional project server training - What defines the baseline?

microsoft professional project server training - What defines the baseline?

ResolvedVersion Standard

Alex has attended:
Project Intro Intermediate course

What defines the baseline?

As above question

RE: what defines the baseline?

Hi Alex

The baseline is a snapshot of your project created when you go to Tools > Tracking > Baselines and choose "save baseline"

Project stores your duration, start, finish, cost and work values for your tasks so that later on you can compare your baseline snapshot against your current position.

You can view this information by switching to the tracking gantt view.

I hope this is helpful - do let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.