microsoft+project+courses - Resource allocation

ResolvedVersion Standard

Wendy has attended:
Project Intro Intermediate course

Resource allocation

Is it better to change max units to 200% if you have 2 people with the same job (e.g. project assistant) or to add the resource twice?

Thanks

RE: Resource allocation

use 200% it is less confusing

MS Project tip:

Set default task type - Project 2010

a. In Project, click on the File tab
b. Select Options from left hand side
c. Click on Schedule to set the scheduling options
d. Set the Default Task type box to your chosen option
i. Generally if you plan/estimate your projects using durations you should use fixed duration, and untick the box New tasks are effort driven, if you plan/estimate with person hours use fixed work, or for plans estimated with the proportion of resources time use fixed units, and untick the box New tasks are effort driven)
e. Click OK to apply your changes

View all MS Project hints and tips