Public Schedule Face-to-Face & Online Instructor-Led Training - View dates & book

STL - Formerly Best Training Solutions Through Learning
TrustPilot
Excellent
Request Callback We will call you back
0207 987 3777 Call for assistance
Your Basket Basket is empty
microsoft-project-training-courses - viewing resource costs

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft-project-training-courses - Viewing resource costs

microsoft-project-training-courses - Viewing resource costs

ResolvedVersion Standard

Caroline has attended:
Project Intro Intermediate course

Viewing resource costs

I have entered a daily cost for my project resources. How can I get those costs to appear in the 'Cost' column in the gantt view?

RE: Viewing resource costs

Hi Caroline, thanks for your question.

In the Gantt chart view click on a column to choose the point where you would like the cost information to be displayed. From the insert menu choose column and from the dialog box that appears select the cost field.

Wherever you assign a resource that has an associated cost to a task, Project will calculate the cost for that task and display it in appropriate cell of the cost column.

Do let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.