how do you cahnge from £ to $

RE: Formatting

Hi Gregory,

Thank you for your question and welcome to the forum.

To change the currency from Sterling to Dollars, go to Tools and Options. Select the View tab and place a $ dollar sign in the Symbol box.

I hope this answers your question.

Regards

Simon

Thu 5 Nov 2009: Automatically marked as resolved.

MS Project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.