How does Risk and Issues relate to MS Project?

RE: MS Project

Hi Munira

Thank you for your question. MS Project doesn't have a dedicated Risk component. The Tracking Gantt view will show you the Critical path which may be of assistance. Project also contains spare fields such as Text1 which can be used to add your own custom data for your tasks.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

MS Project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips