bar styles corrupt

TrustPilot

starstarstarstarstar Excellent

  • Home
  • Courses
  • Promotions
  • Schedule
  • Formats
  • Our Clients

Forum home » Delegate support and help forum » Microsoft Project Training and help » Bar Styles Corrupt

Bar Styles Corrupt

resolvedResolved · Low Priority · Version 2007

Daniel has attended:
Project Intro Intermediate course

Bar Styles Corrupt

The bar style names are shown as corrupt text, how do I correct this?

RE: Bar Styles Corrupt

Hi Daniel,

Thank you for your question.

In the past the following method has worked:

1. Go to Tools and then Customize
2. Select Toolbars
3. Go to the All Commands category.
4. Find the ComAddinsDialog button and drag it onto a toolbar
5. Click that button and untick all the boxes and click OK.
6. Click again on the button and place ticks in all the boxes.

In the past this has reset the names in the format styles box.

I hope this is information is helpful.

Have a good weekend.

Regards

Simon


 

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips


Server loaded in 0.07 secs.