ms+project+training+london - Progress

ResolvedVersion Standard

Saul has attended:
Project Intro Intermediate course

Progress

how do i show actual progress (start / finish dates) on my task bars without doubling the size of my programme?

RE: Progress

Hi Saul

You could modify your bar styles:

Format > Bar styles

then edit your task style, on the text tab, to display the values you are looking for alongside each bar on the Gantt chart

Alternatively, once you have baselined your project switching to the Tracking Gantt view will show you the original project and your current project progress on the same display.

Hope this helps, let us know if you have any further questions.

Kind regards,

Andrew

MS Project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips

Connect with us:

0207 987 3777

Call for assistance

Request Callback

We will call you back

Server loaded in 0.09 secs.