How do you get visibility of the critical path?

RE: Critical Path

Hi Ryan

Thanks for your question. A quick way to see the critical path is to switch to the Tracking Gantt view (View > Tracking Gantt) This shows your critical tasks in red and non-critical tasks in blue.

I hope this helps - let us know if you have any further questions.

Kind regards,
Andrew

Tue 3 Feb 2009: Automatically marked as resolved.

MS Project tip:

Avoid Accidental Constraints

The initial default table is the Entry table. Enter a task name and duration, but do not enter start or finish dates. Form the plan using links, predecessors. Typing dates introduces constraints. To remove these constraints, double click on a task, and on the Advanced page of Task Information set the constraint back to As Soon As Possible (all other options are there too.)