Milestones
How do you enter a milestone
RE: milestones
enter the duration Zero
Forum home » Delegate support and help forum » Microsoft Project Training and help » microsoft projects courses london - Milestones
val has attended:
Project Intro Intermediate course
Project Intro Intermediate course
How do you enter a milestone
enter the duration Zero
a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.