client milestone

ResolvedVersion 2003

Antoine has attended:
No courses

Client Milestone

Hello, I would like to know how to change automatically my milestones into client milestones (Different shape and colour)

It works with the bars (Customize-Fields-Flag)+ adding in the bar style but whwn I do it with the milestones, nothing happens, it stays the some shape and colour of the normal milestone.

Have you got any ideas?

Many thanks

RE: Client Milestone

Hi Antoine

Thank you for your question.

There are two additional things you need to do once you have allocated your flag field and formatted the bar style

1. You need to change the bar style format so that the "from" and "to" fields in the bar styles dialog both say start.
2. For each client milestones you need to bring up the task details dialog and remove the "mark as milestone" tick on the advanced tab

This should then work

Regards

Stephen

MS Project tip:

Create own ribbon tab - Project 2010

a. In Project click on the File tab
b. Select Options from left hand side
c. Choose the Customize Ribbon section
d. Click the New Tab button (below the list of tabs on the right hand side of the dialog box)
e. Select the New Tab (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
f. Select the New Group (Custom) and enter a name, by clicking the Rename button (below the list of tabs on the right hand side of the dialog box)
g. Add commands to your tab and group by locating them on the list on the right hand side (remembering that you can change the list using the drop down box at the top of the list of commands) and clicking the Add button between the two panes to add them to your tab and group
h. You can rearrange the commands in your group, the groups on any tab or the tabs, using the up and down arrow buttons beside the list of tabs.
i. Click OK to apply your changes

View all MS Project hints and tips