How do you put the Critical Path view of your Gantt plan into 'other Views'? Effectivley creating a seperate Gantt chart for your Critical Path

RE: Microsoft Project

Hi Ron

Thank you for your question

I suggest the following procedure

Click on more views at the bottom of the view bar
Click New
Choose single view and continue
Give your view a suitable name
Select the entry table
Set the group to No Group
Set the filter to Critical
Tick the check box to show the view in the menu

Click OK

Your view will then appear on your view bar

Hope this helps

Regards

Stephen

RE: Microsoft Project

Stephen
Thanks it works.

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips