Forum home » Delegate support and help forum » Microsoft Project Training and help » ms+project+training - Linking

ms+project+training - Linking

ResolvedVersion Standard

Beata has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Linking

How to get to 'start to start' linking?

RE: Linking

Link the two tasks, click on the task link arrow in the Gannt Chart, (the line joining the 2 boxes), and in the drop down, select start to start, click on "OK"

MS Project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.