project calendar

ResolvedVersion 2003

Danielle has attended:
Project Intro Intermediate course

Project Calendar

Can the calendar from Project be emailed or transferred to Outlook?

RE: Project Calendar

Hi Danielle

There isn't a direct connection from the Project Calendar to Outlook's calendar. One option would be to export the data from Project (File > Save As ) using CSV and then importing it into Outlook.

If you have any further questions please do let us know.

Thanks

Andrew

MS Project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.